Kier turned to Morson Vital to support the delivery of the £19m SIN 119 HV rail civils project in Gobowen. Spanning 2.5 years, the programme demanded experienced teams, disciplined site delivery and long-term workforce continuity. Morson Vital provided all three, deploying embedded rail civils capability that supported safe, efficient delivery from start to finish.

The challenge

Kier required a highly capable, safety-led civils workforce to deliver the SIN 119 HV Project in Gobowen. The programme was complex, long-term and mission critical. It demanded consistent productivity, deep rail civils expertise, and the ability to scale resource without disrupting live operations.

The margin for error was minimal. Delivery had to stay on programme while meeting strict safety, quality and operational standards.

The Morson Vital solution

Morson Vital deployed a fully integrated rail civils delivery team, embedded from project inception through to completion. Our role focused on providing experienced, site-ready capability that could operate at pace while maintaining absolute control over safety and quality.

Across 2.5 years, we supplied and managed 28 full-time contractors, structured into skilled, self-sufficient gangs and supported by experienced supervision and plant operations. Our long-standing relationship with Kier allowed us to mobilise quickly, align to site processes, and maintain continuity throughout the programme lifecycle.

Scope of works delivered

Morson Vital-supported teams were responsible for a broad range of rail civils activities, including:

  • Installation of a new line of route to improve connectivity and operational efficiency

  • Replacement of damaged troughs and lids to restore asset integrity

  • Construction of new concrete bases supporting rail infrastructure and equipment

  • Route elevation works to meet safety and compliance requirements

  • Installation of new Power Signal Boxes to enhance signalling reliability

  • DNO route works to support efficient power distribution

  • Construction of location cabinet bases for secure electrical and communications housing

  • Staging construction to enable safe, efficient site operations

  • Footpath development to improve access for operatives and passengers

  • Installation of chambers housing critical infrastructure components

All works were delivered safely, sequentially and in line with programme milestones.

Workforce model

The project was delivered by a structured, experienced team comprising:

  • 4 x five-person skilled lineside civils gangs

  • 1 x Supervisor

  • 1 x Telehandler Operator

  • 1 x Bankman

  • 1 x Storeman

This model ensured on-site resilience, productivity and clear accountability at every stage.

Outcomes

£19m rail civils project delivered successfully over 2.5 years

Stable, safety-led workforce embedded from start to finish

Zero disruption from resourcing constraints

Long-term client confidence reinforced through consistent delivery

The results

The Kier Gobowen project demonstrates Morson Vital’s ability to deploy expert rail civils teams at scale, over extended timeframes, and in demanding live environments. Our combination of sector knowledge, delivery discipline and long-standing client partnership ensured the project stayed on track and performed as intended.

Mission critical rail civils. Delivered with certainty.

At Morson Vital, technology is more than a tool, it’s how we protect, empower, and connect our workforce. Whether it’s […]

Every project needs protection. From safeguarding critical infrastructure to securing worksites and preventing disruption, professional security is vital to keeping […]

At Morson Vital, project delivery means more than supplying labour. We take responsibility for planning, mobilising and executing defined work […]

In today’s competitive skills landscape, securing the right talent fast is mission-critical. Our Recruitment and Staffing teams have over 40 […]

From national infrastructure to local regeneration, we deploy the skilled people who keep projects moving. Whether it’s scaffolding operatives for […]

Mechanical, electrical, and instrumentation (ME&I) projects demand specialist expertise, from high-voltage substations to offshore oil platforms. As one of the […]

At Morson Vital, we specialise in the supply of temporary and permanent personnel for 11–400kV projects across the UK and […]

The rail network never stops. To keep passengers and freight moving safely, infrastructure must be maintained, upgraded, and secured by […]

Explore further

To top